Construction Impacts
Projects of Note
I-95 On Ramp Closed
The I-95 southbound on ramp at Exit 7 from Market Street will be closed through Wednesday, July 2 to complete construction related to the NHDOT soundwall project.
Paving
Mon Jun 30 -- Church Street
Tues Jul 1 -- Islington Street/Maplewood Avenue intersection, Porter Street
Wed Jul 2 -- stripe Church and Islington Streets
Hanover Garage
Work continues on the application of pavement markings on Level 2. The Hanover Garage is in year two of a three-year renovation. Questions? Contact the Parking Office at 603-610-7257. Go to the Hanover Garage Project page for more information.
Sylvester Street Sewer Line Installation
Final work on new gravity sewer line, extending from the existing manhole at the bottom of Sylvester Street into the wooded area. Project equipment and material laydown area will be located on Chase Home property, ensuring that only essential equipment and materials needed for the Sylvester Street portion of the construction will be in the road. Affected homeowners are being notified of the construction. Access will remain open.
Seasonal Construction Project Updates
No construction work planned for Friday, July 4 in observance of Independence Day.
Islington Street
Week of June 30: Phase 2b Construction Area Section 1- Cornwall Street to Langdon Street: No work anticipated. Section 2 – Langdon Street to Maplewood Ave: Paving preparation on Maplewood intersection. Final Paving on Maplewood Avenue, Porter Street and Islington Street tentatively scheduled for Tuesday, July 1 (weather permitting). Brick sidewalk work near Maplewood Avenue. Holiday traffic preparation and clean up. Section 3 -- Legion to State Street: Possible drainage main installation. By the end of the summer season, all portions of the Islington Street project should be complete. For the project overview: March 19, 2024 public meeting presentation and video recording, additional background information and to sign up to receive weekly updates on the project, visit the project page.
Sagamore Avenue Sidewalks
This project consists of constructing a new sidewalk along the NHDOT roadway of Sagamore Avenue from approximately 1171 Sagamore Avenue to Odiorne Point Road. Road paving anticipated after the July 4 holiday. For details go to the meeting recording and minutes. For more information, visit the project page.
Summit Avenue Sidewalk
This project consists of constructing a new sidewalk along Summit Avenue from the High School gated entrance to South Street. Concrete work will begin July 7 and is anticipated to continue throogh August 15).
Bartlett Street
The final placement of paving and site restoration on Bartlett Street is scheduled, tentatively to proceed as follows: July 7-18 -- Punchlist items, sign installation, construction of manhole inverts. Week of July 21 – Milling multiple tie-in locations at limits of the project, raising structures to final pavement height. Week of July 28 – Placing final asphalt and constructing raised crosswalk and raised intersection. Week of August 4 – Final pavement markings. The Morning Street scope of work is currently on HOLD and will be reevaluated along with future phases of work in the Creek Neighborhood. For the March 27, 2024 public meeting presentation and video recording, additional background information and to sign up to receive weekly updates on the project when it starts, visit the project page.
Maplewood Avenue Bridge
The bridge remains closed at the start of the week as work to install the bridge rail is completed and temporary paving and striping for one-way traffic is applied. The bridge is expected to open to one-way, inbound-to-downtown, vehicular traffic at 4 pm on Thursday, July 3. Pedestrian access will be maintained at all times. Currently, pedestrians are using the southern sidewalk; access is anticipated to switch to the northern sidewalk at the end of day on July 3rd. The balance of the bridge work will continue on the south side through November as the contractor replaces the sidewalks and railings. Pedestrians and cyclists (walking their bikes) will have access across the bridge on whatever side is not currently under construction. For detour options, the meeting presentation, design plans, additional background and to sign up to receive weekly updates on the project when it starts, visit the project page.
Union Street
Paving is complete. Pouring the concrete sidewalk at the southern intersection of State Street and Union Street will take place after the holiday. Weeds will be managed and loamed areas will be re-seeded in the fall. Following up on punchlist items. For more information in the April 2, 2024 meeting presentation and video recording and to sign up to receive weekly updates on the project when it starts, visit the project page.
Willard Avenue Project
Week of June 30: Remove temporary asphalt from the driveways, grade, and re-pave. Concrete walkways will be finished as soon as possible. All sewer testing is complete. A public information meeting on the 2025 project work was held on April 2. Go to the meeting presentation and video recording from that meeting. For the original project preconstruction meeting presentation and video recording, more information and to sign up for future email updates, visit the project page.
Middle/Miller/Summer Street Intersection Signals
Construction is expected to start in September 2025. Electric Light is the contractor. For more information, visit the project page.
Little Bay Road Water Main Replacement
This joint project with the Town of Newington involves the installation of an eight-inch ductile iron water main and the replacement of 25 water services and four hydrants. Upon completion, the road will be patched and prepared for final pavement by the Town of Newington. The project is scheduled to be completed by mid-summer. A public information meeting was held on April 8, 2025 at the Newington Town Hall (336 Nimble Hill Rd, Newington, NH 03801). For more information, visit the project page.
NHDOT Projects in Portsmouth
I-95 Sound Barrier Construction
Work to install the sound wall continues. Exit 7 ramp, southbound onto I-95 from Market Street will be closed through Wednesday, July 2 for construction related to the project. Governor Sununu and the Executive Council at their September 25, 2024 meeting authorized the NH Department of Transportation (NHDOT) to enter into a contract with Northeast Earth Mechanics, LLC of Pittsfield, NH for the construction of sound abatement walls and privacy fencing along I-95 in Portsmouth. The contract amount is $18,771,486.75. For full details and background visit the project page.
NHDOT Lafayette Road (Route 1)
NH Department of Transportation (NH DOT) presented updated plans for its Lafayette Road (Route 1) Corridor Improvement Project to the City Council on May 5. For background visit the Project Website (Portsmouth 29640) with the full US Route 1 Corridor Plan. NH DOT also advises that anyone with comments or concerns about this project should contact David Smith, P.E. - Project Manager, NH Department of Transportation | P.O. Box 483, Concord NH 03302